some unsolicited thoughts on the problem at hand
July 24, 2022
A Few Thought on the Radar Integration for BMD
New element means new learning
Introducing a new element to AWS has had varying success. CEC, SM-6, SM-3 all came with different challenges. This integration will have some surprises, but relooking the success and challenges of the prior integrations may help avoid repeating prior mistakes, and hopefully help avoid some new mistakes.
The new integration will have some challenges and failures, just don’t pay to learn the same thing again.
Understand the element is new and has lots to learn
The lexicon, working with the other elements, etc., is all new. It is going to take deliberate socialization and leadership to bring the element fully into the AEGIS working party. Do not expect them to know the 25+ year history of AEGIS BMD performance.
Frustration for existing elements
1. The other parts of AWS have been working at a PHD level. Now you introduce a new element that is starting at the beginning – no matter how many other radars they have developed.
2. There will be a push from existing elements (and the test community) to skip over some of the basic integration tests1. The existing system has already done the XYZ back flip – 1 target. With the new radar, now time to do the XYZ backflip -2 target. No – time to go back to some basics.
Frustration for the new element
1. The team has been working together for 25-ish years in BMD alone, longer for air defense. The new element will be expected to “know how things are done”. And that will not be how they learned to do it. So there will be cross frustration.
2. “Because it is the way we have always done it” will not be a good enough answer to the noob. This presents an opportunity to re-establish the discipline of the “AEGIS way.”
3. The new radar team will claim they have umpteen successful THAAD, PATRIOT, etc., missile intercepts. But how many from a moving, 360 degree ship, manned by Sailors, etc.? Zero.
Modeling and Simulation
1. The expectation is that by now high-fidelity mission models are running end-to-end. Target -> Radar -> remainder of AWS -> missile -> kill assessment, etc. By the time of FM-2, the models had been run and polished to the point that differences from the actual mission were in small % numbers. And there was immediate interest in understanding even those small deltas.
2. Will the M&S results pass the “Don Mitchell” test2?
3. Are there failures in the M&S results? If every run is successful, no failures, then the models are not accurately capturing system performance. One failed run is probably more interesting than 100 successful. Learning comes from faiilure, and we want to keep all the failures on the ground. What did we learn?
Team Integration
1. One of the best ways to resolve issues early is sharing early results, software before it is final, M&S results when everything is not perfect, etc. But the downside of early sharing is vulnerability – letting others see your product when it is not working right, not polished. In a poorly functioning team, this leads to fingerprinting and blame. Then there is the contract – it typically only specifies final results. The upside of early sharing is early detection of issues, but it takes leadership finesse to cultivate the team to this behavior – it does not come naturally.
2. Consider ways to help the teams integrate with the new element. Maybe explicitly assign liaison officers from the other components, etc. Silos are natural, open teams take cultivation.
Look at the Basics
1. In AEGIS LEAP Intercept, there was deliberate build up from very basic level to target intercept. These were captured at a high-level in the bubble charts. Steps like
- tracking target on single array face
- tracking target across array face transition
- generating missile initialization message
- etc. (These from memory, but the originals should be around somewhere)
It is worth going back with the new element and ensuring that each of these building blocks is properly understood, supported, and functions properly in the integrated M&S environment.
2. In FM-2, neither target nor missile was allowed an array face transition. What are the correct steps to build up with this new radar?
3. The other team members will be frustrated having to go back to basics. Will take leadership to hold them back while the new element takes first steps.
4. The counterpoint is that from FM-2 to FM-7 there was huge acceleration, enabled by the success of FM-2. Slow down, focus, attention to basics, get the first one right, then have a measured acceleration to full capability. FM-5, 6, 7 each had a number of large steps to full tactical employment by FM-7.
5. There were nay-sayers against some of the non-tactical constraints in FM-2. But we were not deploying the FM-2 system. Without the success of (and system understanding from) FM-2, the road to tactical deployment would have been much longer and harder.
Build a little, test a little, learn a lot, then run fast.
Schedule
How realistic is the complete integration schedule? Are there real feeds from an Integrated Master Schedule (or even heroics by a scheduler doing manual component schedule integration), or is it just PowerPoint hope and fiction?
Contract
This is always the sticky wicket. Do the contracts incentivize the team performance desired? Probably not. They were typically written in a stove pipe. But there is always a way to resolve the problem. What about adding the senior contracting official to the panel for key reviews? MCPs, MRR, or whatever they are called today. Contracts will be a key part of success or failure, and needs to join the front line effort.
Warroom
Long since forgotten, but the IDO War Room provided a single integrated view of the path to success. Again, full open kimono. Schedule (IMS) Review was a key portion of weekly engagement by the flags. A proper war room requires several Jim Speers and Kris Kennedys to function properly, it is not an apprentice task. And a computer monitor or two does not provide the integrated view of having everything on the wall. Anyone could visit the war room, industry, OSD, DOT&E, etc.
Deep Dive Candidates
A few areas to look at in particular (starting with do these terms even mean the same thing to the new element?)
- radar doctrine management, configuration, etc. Everything in getting the radar on target and into track
- radar control loop
- fire control loop
- missile uplink & downlink management
- array face transitions, especially wrt target tracking, missile tracking, missile uplink
The Team is starting at zero for zero
A thought for leadership – the AEGIS BMD team has umpteen successful intercepts. The radar team has their successes with other systems.
No one has any successful attempts with this new system – you are starting at zero for zero. So failure is not a decimal point reduction in success rate, but means success rate is exactly 0%. How does leadership get the hunger of FM-2 back into the team? Failure meant Mitch Crosswise of PA&E, et. al, would take away all our money. (But not to the point of scaring the team into test paralysis, like happened with the early GMD team.).
Everyone was fully invested in the success.
- This did happen with SM-3 Blk IB, and was surprisingly difficult to change course.
The first target the test community wanted to present for SM-3 Blk IB was outside the specification threat space, and leadership jumpted on board with it. “We spent all this $$ on the new missile, and you cannot engage it? We wasted public $!”
No – we needed to ensure the T-DACS works in space FIRST, then build up to the complicated threats. (Build a little, test a little, etc.)
Of course, turns out the TSRM blew up in that mission, not even a new component in the test.
And what are the contractural implications of failure against a target not in the threat set. This is not where you want to be on the first outing.
↩︎ - I still know of no one who could identify a weakness in end-to-end modeling or data analysis like Don could. ↩︎